Traditional overhead allocation

Content revised on 3 October 2026. Any completion marker earned before this revision refers to the earlier content version and does not confirm completion of this revised lesson.

Learning goals

  • Calculate plantwide and departmental overhead assignments.
  • Explain redistribution and assess driver suitability.

Assumptions and scope

  • Budgeted complete allocation; all driver quantities belong to this period.
  • No WIP, sales or actual overhead differences are being valued here.
  • Driver relationships are assumed for practice; they require operational validation in a real system.

Content revised on 3 October 2026. Any completion marker earned before this revision refers to the earlier content version and does not confirm completion of this revised lesson.

Traditional overhead allocation commonly uses one volume-related driver, such as labor hours or machine hours, to distribute a manufacturing support pool. A plantwide rate combines the entire defined pool. Departmental rates keep selected pools separate and may use different drivers. The arithmetic is similar in both cases; the substantive choice is whether one activity measure reasonably represents the resources being assigned.

Begin by defining the pool. Include each cost once and identify any costs deliberately excluded. Then choose a driver whose data can be recorded consistently and whose relationship to the resources is defensible. A machining department may use machine hours, while an assembly department might use labor hours. Physical convenience is not sufficient justification: a readily available driver can still produce a distorted result if products use the support resources very differently.

Divide each budgeted pool by its corresponding budgeted driver quantity. Assign cost to a product by multiplying the rate by that product's consumption of the same driver. If a product crosses several departments, calculate each departmental assignment separately and add them. Label every rate with its unit; a rate per labor hour cannot be multiplied by machine hours merely because both quantities happen to be called hours.

A plantwide system can be adequate when products consume resources in broadly similar proportions. It becomes more questionable when one product is machine-intensive and another is labor-intensive, or when complex small batches cause substantial support work unrelated to unit volume. Departmental rates can improve the description but are not automatically correct. A department itself may contain different support activities that need further analysis.

Compare methods by holding the total pool and production mix constant. Reconcile the sum assigned to all products under each method to the same budgeted overhead. A product's cost can rise under one method while another's falls, with no change in total spending. Describe this as redistribution. Calling it a saving would confuse a change in measurement with a change in resources. Price and product decisions require additional demand, capacity and avoidability evidence.

Finally, review the denominator. A rate based on expected activity embeds a capacity assumption. If expected activity drops while the pool stays unchanged, the computed rate rises even without an increase in resource prices. Reports should show the driver volume as well as the rate so managers can see that effect. The exercises here use complete budgeted allocations with no actual-versus-applied adjustment; later variance work deals with that separate issue. Keep the allocation model, the period's actual results and the decision to be made clearly identified in your explanation.

Concept verification: [OpenStax, predetermined overhead](https://openstax.org/books/principles-managerial-accounting/pages/4-4-compute-a-predetermined-overhead-rate-and-apply-overhead-to-production): a budgeted rate can assign overhead during production; verified 3 October 2026. Original course examples.

Worked example: Worked example: Machine-intensive and labor-intensive products

Budgeted machining overhead is 2,400 MU for 300 machine hours; assembly overhead is 1,600 MU for 200 labor hours. Product P uses 200 machine hours and 50 labor hours; Q uses 100 machine hours and 150 labor hours. Compare departmental assignment with one 4,000 MU plantwide pool using labor hours.

Solution

Departmental rates: machining 2,400 / 300 = 8 MU/machine hour; assembly 1,600 / 200 = 8 MU/labor hour. P receives 200 × 8 + 50 × 8 = 2,000 MU; Q receives 100 × 8 + 150 × 8 = 2,000 MU. Plantwide rate = 4,000 / 200 = 20 MU/labor hour. P receives 1,000 MU and Q 3,000 MU. Each method totals 4,000 MU. Departmental allocation shifts 1,000 MU from Q to P relative to the plantwide method.

Traditional overhead allocation reference table

Read by row; each named column is a text label. Monetary figures are fictional MU. This table is also available as plain text.

Product Plantwide MU Departmental MU Departmental minus plantwide MU
P 1000 2000 1000
Q 3000 2000 -1000
Total 4000 4000 0

Independent practice

  1. A budgeted support pool is 1,800 MU for 300 machine hours. Products A and B use 120 and 180 hours. Find rate and assignments.

  2. A job uses 12 machining hours at 9 MU/hour and 7 assembly hours at 6 MU/hour. Find its departmental overhead.

  3. The same budgeted pool of 3,000 MU is divided by either 500 expected hours or 600 expected hours. Find both rates and explain why this is not evidence of a spending reduction.

Practice answers and reasoning
  1. 6 MU/hour; A 720 MU; B 1,080 MU.

    The driver totals 300 hours and the assignments reconcile to the 1,800 MU pool.

  2. 150 MU.

    108 MU machining plus 42 MU assembly; keep each rate paired with its own driver.

  3. 6 MU/hour at 500 hours; 5 MU/hour at 600 hours.

    The numerator is unchanged. Only the activity denominator changes, so the pool’s resource cost has not fallen.

Common errors to avoid

  • Selecting a driver only because it is convenient to collect.
  • Comparing methods with different cost pools and attributing the entire difference to allocation.

Exit check

  1. What must match the unit on a rate?

  2. If one product gets less overhead after a method change, did the business necessarily save money?

Exit-check answers
  1. The activity quantity used to apply it.

    Machine-hour and labor-hour rates are not interchangeable.

  2. No.

    Reallocation can reduce one product’s assignment and increase another’s without changing total resources.