Job-cost records
Content revised on 3 October 2026. Any completion marker earned before this revision refers to the earlier content version and does not confirm completion of this revised lesson.
Learning goals
- Build cumulative job costs and identify their inventory location.
- Reconcile job records to WIP and completed output.
Assumptions and scope
- Fictional MU; no opening finished goods, spoilage, returns or inventory write-downs.
- Alder units are identical and no units are sold.
- Provided overhead amounts are applied cost; no period adjustment in this lesson.
Content revised on 3 October 2026. Any completion marker earned before this revision refers to the earlier content version and does not confirm completion of this revised lesson.
A job-cost record gathers costs for a distinct order or project. The job must have a stable identifier that appears on its material issues, labor records and completion documentation. Its costs may cross a month end, so a job's cumulative cost and the month's additions are different measures. A record should show both. Otherwise, a reader may mistake the full job total for current-period production spending.
Begin with the opening balance if work was already underway. Add direct materials supported by issue records, direct labor supported by time and pay records, and overhead according to the stated assignment policy. Do not add the customer's payment or the selling price to this cost sheet. Those belong to the revenue and receivables side of the transaction. A profitable job is not a cheaper job merely because the customer paid promptly.
The status of the job determines where its cumulative cost belongs. An unfinished job remains in WIP. A manufacturing job completed but not sold moves to finished goods. A sold job moves to COGS. A service project may have a different delivery pattern, which must be stated. A completion date therefore performs an accounting function as well as an operational one. The underlying job identifier should remain available after transfer for later review.
A batch can be a single job even though it contains several identical items. Divide the completed batch cost by the number of acceptable units in that batch to calculate a batch average. This is not necessarily the cost of making an extra item: setup and other shared costs may not increase proportionately. If units have different designs or resource requirements, a simple equal split can be misleading and the system may need sub-jobs or another allocation rule.
At period end, reconcile the subsidiary records with the control accounts. Add the unfinished job balances and compare that sum with WIP. Add completed unsold job balances and compare with finished goods. Investigate missing job numbers, unapproved time, duplicate material issues and transfers posted to only one side. A spreadsheet total that balances against itself is weaker evidence than a comparison with independently maintained source records.
Job costing also supports learning. Compare estimated and actual hours, record authorized changes in scope, and distinguish a genuine overrun from an approved customer modification. A cumulative cost sheet alone cannot explain why spending increased. The reviewer needs the original estimate, the revised specification and operational evidence. In this course, overhead is assigned using a provided rate and all job quantities are acceptable units; later lessons examine rate construction and cost differences. Keeping that boundary explicit lets you practice the control logic without pretending that every real production complication has been solved.
Concept verification: [OpenStax, job and process costing](https://openstax.org/books/principles-managerial-accounting/pages/4-1-distinguish-between-job-order-costing-and-process-costing): production cost records distinguish traceable job costs from pooled costs; verified 3 October 2026. Original course examples.
Worked example: Worked example: Two jobs at month end
Job Alder opens in WIP at 200 MU; this month it receives 500 MU materials, 300 MU labor and 150 MU overhead. It is completed as 10 identical acceptable units, none sold. Job Birch opens at zero and receives 400 MU materials, 200 MU labor and 100 MU overhead; it remains incomplete. No other jobs exist. Find COGM, ending WIP, finished goods and Alder unit cost.
Solution
Alder cumulative cost = 200 + 500 + 300 + 150 = 1,150 MU, transferred to finished goods and included in COGM. Birch = 400 + 200 + 100 = 700 MU ending WIP. Ending finished goods = 1,150 MU because none of Alder is sold and opening finished goods is zero. Alder average = 1,150 / 10 = 115 MU/unit. Control: opening WIP 200 + current additions 1,650 = completed 1,150 + ending WIP 700 = 1,850 MU.
Read by row; each named column is a text label. Monetary figures are fictional MU. This table is also available as plain text.
| Job | Opening MU | Current additions MU | Cumulative MU | Closing destination |
|---|---|---|---|---|
| Alder | 200 | 950 | 1150 | Finished goods |
| Birch | 0 | 700 | 700 | WIP |
Independent practice
-
Job Cedar has opening cost 120 MU, current materials 280 MU, labor 160 MU and overhead 80 MU. It finishes as 8 identical units. Find cumulative cost and batch unit cost.
-
Three job balances are 900 MU unfinished, 600 MU completed and unsold, and 450 MU completed and sold. There are no other balances. Assign WIP, finished goods and COGS.
-
WIP control shows 2,200 MU. Unfinished job sheets sum to 1,950 MU. A verified 250 MU labor record is in the control account but missing from its unfinished job sheet. What correction and reconciliation are needed?
Practice answers and reasoning
-
640 MU total; 80 MU/unit.
Include the opening cost once: 120 + 280 + 160 + 80 = 640, then divide by 8.
-
WIP 900 MU; finished goods 600 MU; COGS 450 MU.
The same original production cost moves according to status; it is not counted in all three accounts.
-
Add 250 MU to the correct job sheet; reconciled WIP is 2,200 MU.
This repairs the subsidiary omission. Do not also debit the control account again, because it already includes the labor.
Common errors to avoid
- Dropping opening job cost when the calendar month changes.
- Expensing a completed but unsold manufacturing job without the stated policy supporting it.
Exit check
-
Should a customer deposit reduce a job’s production cost?
-
What is the strongest first check on the WIP control balance?
Exit-check answers
-
No.
Payment and production cost are different records.
-
Sum the open job records and reconcile to the control.
Then test the underlying records and cutoff for errors that a matching total may hide.